Welcome to our project page! Here we will keep you up to date on the progress of the construction work on our new administration building with attached production hall in the idyllic town of Moers. Join us on this exciting journey and find out more about the individual construction phases and milestones.
16 oktober 2024
Gate, door and window frames are set
15 oktober 2024
Preparations for roof windows
14 oktober 2024
Additional side cross members were mounted
11 oktober 2024
The roof racks are mounted
10 oktober 2024
Preparation for roof and wall cladding: After the scaffolding is erected, brackets and fastening points for the roof and wall cladding are installed.
8 oktober 2024
The main beams that carry the load of the hall are erected and connected to each other. This is often done with the help of cranes. Cross beams are installed between the main beams to stabilize the structure and distribute the load evenly.
2 oktober 2024
The construction of the hall framework begins: the steel beams are anchored on the prepared foundations to ensure a stable base.
30 september 2024
The base plate has dried and construction work is continuing. Heavy machinery and materials are being delivered.
18 july 2024
The floor slab is in place. Now the concrete has to harden.
11 july 2024
The concrete is delivered as ready-mixed concrete and poured into the formwork. Vibrators or other compaction equipment compact the mixture to remove air pockets and ensure a tight, solid structure.
9 july 2024
Steel reinforcements are placed in the formwork to strengthen the floor slab and prevent cracks.
8 july 2024
We start with the foundation for the new building; set up formwork to keep the concrete in shape.
Planning and approval include drawing up construction plans and obtaining the necessary permits. This is followed by a subsoil investigation, in which the soil conditions are analyzed to ensure the load-bearing capacity. This is followed by earthworks, which include excavation and preparation of the subsoil.